From the sixties to the future Zukunft
In Bolligen, a development dating from the 1960s is being transformed into Switzerland’s first Minergie-Areal development and developed into a future-ready residential neighborhood.
![]()
header.search.error
UBS «Anfos»
In Bolligen, a development dating from the 1960s is being transformed into Switzerland’s first Minergie-Areal development and developed into a future-ready residential neighborhood.

The properties on Hühnerbühlstrasse are undergoing comprehensive refurbishment, with additional stories in timber construction and an upgraded energy concept. A large proportion of tenants will remain in their familiar surroundings during construction.
With an investment volume of around CHF 90 million, the renewal of the residential development on Hühnerbühlstrasse in Bolligen (BE) is currently UBS «Anfos»’ largest construction project. Built in 1960/1961 with originally 200 apartments, the development is being comprehensively modernized and supplemented with an additional story in timber construction. This creates 36 additional apartments, bringing the future total to 236 units.
Refurbishment without leaving home

The works are being carried out in two phases. This approach allows residents to remain in the development during construction. The first phase, comprising 116 apartments, was ready for occupancy as of 1 December 2025. Ninety percent of the units are already leased, around three quarters of them to existing tenants. The second phase, comprising a further 120 apartments, is scheduled for completion in the third quarter of 2027.
A noticeable improvement in residential comfort
The renewal improves everyday life in many respects: adapted floor plans, larger balconies and modern kitchens and bathrooms provide contemporary living comfort. Improved sound insulation ensures greater peace and quiet. In addition, lowered building entrances and new, larger lifts will provide barrier-free access to 100 apartments.
A site with a future
The development’s energy infrastructure is also being comprehensively renewed and aligned with future requirements. The existing oil heating system is being replaced by a connection to the low-CO2 Bolligen-Stettlen district heating network. New windows, improved insulation and photovoltaic installations with an output of around 400 kWp reduce energy consumption. A durable, rear-ventilated facade of corrugated Eternit panels complements the concept.
The upgrading extends beyond the buildings: native plants enhance the quality of green spaces, while charging stations for electric cars and e-bikes expand the mobility offering. Following completion of the works, the development aims to achieve «Minergie-Areal» certification.
Through the comprehensive renewal of the residential development in Bolligen, UBS «Anfos» not only creates additional contemporary, energy-efficient residential space, but also responsibly develops an existing location over the long term. The combination of high construction quality, socially considerate implementation and a consistent focus on renewable energy strengthens the property’s future viability while making a long-term contribution to the quality and diversification of the portfolio.
Apartments upon completion | 236 |
Additional apartments | 36 |
Investment volume | approx. CHF 90 million |
Photovoltaic output | approx. 400 kWp |
Planned certification | Minergie-Areal |
Completion | Phase 1: 1 December 2025; phase 2: third quarter of 2027 |
News in brief
Two new buildings are planned to complement the existing high-rise at Zurmattenstrasse 34, 36 and 38 in Solothurn. More than 50 additional apartments will almost double the current offering of just under 60 units. At the same time, the underground car park will be expanded and the outdoor and green spaces upgraded with native planting, improved pedestrian routes and a new playground. The new buildings are planned with renewable heat supply and solar power generation. The development plan prepared for the project will be made available for public inspection in the coming months before undergoing the cantonal approval process. Approval is also subject to the ongoing revision of the municipal land-use plan becoming legally effective; its entry into force is currently delayed by proceedings pending before the Federal Supreme Court.

Marcin Paszkowski
Fund Manager since 2014
Code: M-007356

Head Real Estate DACH

Head Listed Funds CH

Head Investment Foundations CH

Head International & non-listed Products CH and RE-DA

Head Acquisition & Disposition CH

Head Market Specialists Real Estate DACH